Grid connection delays: how to find capacity and connect sooner.

Find a substation with real headroom, avoid network reinforcement costs and speed up your connection.

Ask a network operator to connect a new solar array or battery and the answer can be a long wait, a large bill for network reinforcement, or both. It's one of the biggest reasons good projects stall. Often, though, the first offer isn't the only option.

Start with where the capacity actually is

Spare capacity varies a lot from one substation to the next. Network operators publish capacity maps and data, but they're a starting point, not an answer. We use our grid capacity insights to help you find a point of connection with real headroom, so you can avoid network reinforcement costs and speed up your connection. And if a site isn't going to connect quickly or cheaply, we'll tell you straight away rather than after you've spent money finding out.

Fit under a smaller connection with a battery

You may not need as big a connection as you think. A battery can store midday solar instead of exporting it, or cover short peaks in demand, keeping your import and export within a smaller limit. Export limitation schemes can do the same for solar on its own. A smaller connection is often quicker and cheaper to get.

Challenge the offer

Connection offers are not always right first time. We go through them line by line: whether the reinforcement works are really needed, whether the costs have been apportioned correctly, and whether a different point of connection would be cheaper. Where the numbers don't stand up, we push back.

Consider the IDNO route

Your connection doesn't have to be owned by the local network operator. An independent distribution network operator (IDNO) can adopt the new connection instead, with the contestable work built by an independent connection provider (ICP). In the right circumstances this can be quicker and cheaper, and the IDNO pays an Asset Adoption Value for the assets it takes on. We make sure that payment comes to you.

Be realistic, early

The UK connections process is going through major reform, and timescales can change. The earlier we look at your connection, the more options you have.